EDUCATION

College of Dupage – Served as the Prime Contractor on this 22 acre project. Selected and managed a group of 18 subcontractors and self-performed all excavation, paving and concrete work. Highlights included customized color concrete work resulting in a DNA pattern outside the science building.

Metea High School – Completed all site work on this two year project including 20,000 tons of asphalt paving, 17,000 ft of curb, 12 tennis courts and running track. While on-site, developed a value engineering alternative design for the tennis courts that saved customer over $100,000.

Lincoln Way North High School – Constructed new parking lot and installed concrete loading docks and sidewalks, Completed a major reconstruction of Harlem Avenue and rebuilt access roads into the high school. Selected and managed 5 subcontractors on site..

Governor State University – Prime Contractor in major reworking of university interior road system. Removing and reconstructing entryway into the university with a large scale decorative concrete turnaround on campus. Selected and managed 6 subcontractors on site.

Addison Trail High School – Executed complete redesign of parking lots and interior roads Created a construction plan in multiple phases so that work could be completed while school was in session without disruptions to class schedules

Minooka Elementary and Middle School – Finished all site work on this new school including asphalt pavement for parking lot, access road construction and all curbing. Planned and built bike paths through the school yard.
 
HOME | ABOUT US | ASPHALT | CONCRETE | EXCAVATION | SURVEY AND LAYOUT | PARKING LOTS | CONTACT US
1949 County Line Road Aurora, IL 60502 - 630-585-7220